This week marks significant progress on our ongoing office fit-out, bringing us closer to the final stages of completion. Here’s an overview of what’s happening on-site:
Progress on Key Tasks:
-
Painting Completion
The painting work continues, ensuring that the office walls and other surfaces receive the final touch-ups and are ready for other installations.
-
Fit Out of Steccawood Walls
The installation of Steccawood walls is expected to be completed this week, adding an aesthetic and functional element to the office design. This feature enhances the office’s overall acoustic and visual appeal. We’ll be diving into its design benefits, and why we chose it for our office in an upcoming blog post. Stay tuned!
-
Electrical Fit Off
The electrical work is ongoing. This step is crucial in ensuring all lighting, power points, and other electrical systems are properly installed and functional before the final handover.
-
Installation of Acoustic Panels
This week also marks the installation of our acoustic panels, which we’ve discussed in previous updates. These panels are designed to improve sound quality in key areas of the office, ensuring a quieter, more productive work environment. The acoustic treatment is essential for open-plan workspaces, helping reduce noise distractions and promoting better focus for our teams.
Read more about the benefits of the acoustic panels in our earlier blog post, here. -
Skirting Installation
Skirting installation is another focus this week, giving the office a polished and finished look while protecting the walls from daily wear and tear.
-
Floor Installation
A major milestone is the ongoing installation of the office flooring. This will provide a solid foundation for the entire space and add to the aesthetic finish of the interior.
-
Burgtec Furniture Delivery
We’re excited to announce that this week sees the delivery of our Burgtec furniture, which we’ve previously written about. Known for its premium quality and modern design, Burgtec will play a key role in bringing the workspace to life, providing functional and stylish pieces that support productivity and comfort. This is a significant step, as the new furniture will allow us to start setting up workstations and collaborative areas.
If you want to know why we chose Burgtec, check out our previous blog, here. -
Installation of Ceiling Tiles
Work on ceiling tiles continues as well. This will ensure that the office has a clean and sleek ceiling finish, contributing to both the design and acoustics of the workspace.
-
Plaster Patching
Patching of the plaster is still in progress. These final touch-ups are important to ensure that all surfaces are smooth and ready for painting or other finishes.
-
Glazing Sliding Doors
The installation of glazing sliding doors is scheduled to be completed. These doors will not only provide functional separation between spaces but also bring in natural light, creating an open and inviting environment.
What’s Next for our office fit-out?
The team is on track, and once this week’s tasks are completed, we will be moving into the final stages of the office fit-out. With the acoustic panels installed and Burgtec furniture in place, the office is really starting to take shape. Stay tuned for more updates as we approach the finish line!